Timeline



First estimate received                    15 February 2014
Deposit paid $3000                         25 February 2014
Deposit Variation                            26 February 2014
Deposit Variation 2                          3 March 2014
Pre-Selection walk through            14 March 2014
Consolidated Tender                        4 April 2014
Consolidated Tender 2                     9 May 2014
Consolidated Tender 3                    19 May 2014
Colour appointment                          6 June 2014
Plans & contract signed                    1 July 2014
Plans sent to council                         7 July 2014
Electrical appointment                    26 July 2014
Council approval                            15 August 2014
ON CONSTRUCTION LIST             29 August 2014
Site pegged                                   05 September 2014
Site cut                                          18 September 2014
Piering done                                  22 September 2014
Slab poured                                   27 September 2014
Frame Commenced                       13 October 2014
Frame completed                          17 October 2014
Windows/ sliding doors installed    23 October 2014
Brickwork started                         06 November 2014
Brickwork finished                        21 November 2014
Fascia & gutters installed              22 November 2014
Roof completed (1 day)                25 November 2014
Electrical rough-in                        02 December 2014
Inspection with SS                       05 December 2014
Gyprock finished                          20 December 2014
Internal doors fitted                      13 January 2015
Front & Garage door fitted           15 January 2015
LOCKOUT                                   16 January 2015
Kitchen & Laundry cabinets inst.  21/January 2015
Walk thru with tiler                       21/January 2015
Tiling completed                           31 January 2015
Practical Completion Inspection    10 March 2015

1 comment: