Timeline
First estimate received 15 February 2014
Deposit paid $3000 25 February 2014
Deposit Variation 26 February 2014
Deposit Variation 2 3 March 2014
Pre-Selection walk through 14 March 2014
Consolidated Tender 4 April 2014
Consolidated Tender 2 9 May 2014
Consolidated Tender 3 19 May 2014
Colour appointment 6 June 2014
Plans & contract signed 1 July 2014
Plans sent to council 7 July 2014
Electrical appointment 26 July 2014
Council approval 15 August 2014
ON CONSTRUCTION LIST 29 August 2014
Site pegged 05 September 2014
Site cut 18 September 2014
Piering done 22 September 2014
Slab poured 27 September 2014
Frame Commenced 13 October 2014
Frame completed 17 October 2014
Windows/ sliding doors installed 23 October 2014
Brickwork started 06 November 2014
Brickwork finished 21 November 2014
Fascia & gutters installed 22 November 2014
Roof completed (1 day) 25 November 2014
Electrical rough-in 02 December 2014
Inspection with SS 05 December 2014
Gyprock finished 20 December 2014
Internal doors fitted 13 January 2015
Front & Garage door fitted 15 January 2015
LOCKOUT 16 January 2015
Kitchen & Laundry cabinets inst. 21/January 2015
Walk thru with tiler 21/January 2015
Tiling completed 31 January 2015
Practical Completion Inspection 10 March 2015