Friday, 26 September 2014

             Pleasantly surprised to find the piering completed on Monday. We had an allowance of 70 lineal metres but it only came in at 38, so that will be a big saving. The slab preparation and waffle pods was completed on Thursday and the Slab poured today ( Saturday ).
             When the slab has set the site will be handed back to us to the address some retaining wall issues which I an not looking forward to. Oh well, knew it would have to be done sometime!!!





















                     
                                                        Storm water pipes